A Type, Size, and Location (TS&L) study is one of the most important — and most time-consuming — deliverables in early bridge project development. Done manually, it can take a senior engineer one to two days to assemble: site data gathering, span arrangement calculations, girder selection from published tables, cost estimating from unit price databases, formatting the report.
This guide walks through the full process of a TS&L study, explains what each step requires, and shows where the manual process can be compressed without sacrificing technical rigor.
A TS&L study (sometimes called a "bridge type study" or "structure type study") is a preliminary engineering document that answers three questions:
The study typically evaluates two to four alternatives, provides a cost estimate for each, and recommends one alternative to carry into final design. State DOTs usually require a TS&L report before authorizing PS&E (Plans, Specifications, and Estimates) funding.
Gathering these before sitting down saves significant rework:
| Input | Source | Why It Matters |
|---|---|---|
| Total crossing length (ft) | Survey or aerial measurement | Drives span count and girder type range |
| Deck width (ft) | Roadway section / typical section | Controls number of girder lines and deck cost |
| Number of traffic lanes | Project traffic study | Sets minimum deck width and live load configuration |
| Hydraulic clearance (ft) | Hydraulic report or FHWA scour analysis | Controls minimum superstructure depth and pier placement |
| Pier location constraints | Survey, utility as-builts, railroad agreements | May force longer spans or unequal span arrangement |
| Seismic design category | USGS hazard data + AASHTO LRFD Table 3.10.6-1 | Affects substructure type and detailing requirements |
| State location | Project data | Drives regional cost multipliers and standard girder availability |
The span arrangement — number of spans and individual span lengths — is the first major decision in a type study. It controls:
The practical starting point for most highway bridges is:
For a balanced multi-span arrangement, the rule of thumb is that end spans should be approximately 75–80% of the interior span length to equalize dead load deflection and minimize uplift at interior piers.
For spans under approximately 175 ft, precast prestressed concrete wide-flange girders are typically the most economical choice in most US regions. Steel plate girders become competitive above 130–150 ft and are preferred when depth is constrained (shallow superstructure required) or when very long spans are unavoidable.
| Girder Section | Depth (in) | Practical Span Range (ft) | Notes |
|---|---|---|---|
| WF36TDG | 36 | 40–65 | Short spans, low dead load |
| WF42TDG | 42 | 55–80 | Common for short bridges |
| WF50TDG | 50 | 65–95 | Workhorse section for 2–3 span bridges |
| WF58TDG | 58 | 80–115 | Most commonly specified section |
| WF74TDG | 74 | 100–145 | Long-span precast, may require special haul permits |
| WF83TDG | 83 | 120–165 | Approaching maximum precaster capability |
| WF95TDG | 95 | 140–180 | Maximum standard section; limited precaster availability |
Girder spacing is the key transverse dimension. It drives:
Typical girder spacing ranges from 6 ft to 12 ft on-center. Wider spacing reduces the number of girders and saves cost — until the deck slab becomes the controlling cost element (typically above 10–11 ft spacing for an 8-inch deck). The minimum number of girder lines for a standard two-lane bridge (28–32 ft deck) is typically four to five.
A TS&L cost estimate is a Class D estimate — it is expected to be within ±20–30% of final bid price. The components to price are:
| Component | Unit | Rough National Range (2025–2026) |
|---|---|---|
| Precast concrete girders (furnished & erected) | $/LF of girder | $150–$280/LF depending on section |
| Cast-in-place concrete deck | $/SF of deck | $55–$100/SF |
| Abutments (concrete) | $/EA | $150K–$600K depending on height and foundation type |
| Intermediate piers (hammerhead) | $/EA | $200K–$500K depending on height |
| Traffic barriers (concrete) | $/LF | $45–$85/LF each side |
| Approach slabs | $/EA | $20K–$60K each end |
| Mobilization | % of total | 5–10% of construction cost |
Apply a regional multiplier for your state — costs in the Pacific Northwest or Northeast can run 20–35% higher than the national base; costs in the Southeast or Mountain West can run 10–20% lower. State DOT cost data reports (published annually by most DOTs) are the best source for current regional unit costs.
Every TS&L alternative should be screened against practical constructability factors that can eliminate an otherwise acceptable structural type:
The TS&L report ends with a recommendation of one alternative to carry into final design. A strong recommendation includes:
Manual process: 12–24 hours of engineering time for a 2–3 span highway bridge, excluding project management and document formatting.
With Bridge Copilot: Under 60 minutes for the core engineering computations. The engineer's time shifts from calculation to judgment — reviewing the generated alternatives, applying site-specific knowledge that the tool cannot have, and writing the narrative recommendation.
Generate three preliminary bridge alternatives, with cost estimates and Monte Carlo risk analysis, in under five minutes. No download, no setup, no credit card.
Try the Interactive Demo Start Free Trial© 2026 Bridge Copilot LLC — Home · How It Works · Blog · Privacy Policy